DEMO Sample Project Portal · 47 Oak Street, Samford Valley QLD
Real customer portal looks like this on completion of every job.
PROJ.7421 Tile-to-Colorbond Conversion
47 Oak Street, Samford Valley
202m² · Klip-Lok 700 · Colorbond Monument · Brighte 5-Year Plan · 5 Days On Site · Signed Off 08 May 2026
Status
Complete
SEC.01 Daily Drone Timeline
Five Days, Photographed.
Every morning starts with a drone pass. Every evening ends with a clean-site photo. You see what we see — every day, no waiting for the final report.

D.01 Mon · 04 May 2026
Strip & Make Safe
Old concrete tiles removed. Skip on driveway. Tarp in place for tonight's forecast rain.

D.02 Tue · 05 May 2026
Battens & Sarking
Steel top-hat battens installed at 600mm centres. Bradford Anticon sarking laid and taped.

D.03 Wed · 06 May 2026
Insulation Upgrade
Existing R3.5 batts upgraded to R5.0. Whirlybird relocated to optimise extraction over the kitchen.

D.04 Thu · 07 May 2026
Sheet Lay
Lysaght Klip-Lok 700 in Colorbond Monument. 14 sheets, custom flashings cut on-site for the dormer.

D.05 Fri · 08 May 2026
Capping & Sign-Off
Ridge capping fixed. Site cleaned. QBCC compliance pack and warranty cert signed off.